10×12 ft Material Takeoff

10×12 Concrete Slab Calculator: Bags & Yards Takeoff

A 10×12-foot concrete slab (120 sq ft) at a 4-inch depth requires 1.48 cubic yards of concrete, which translates to 67 bags of 80-lb concrete or 89 bags of 60-lb concrete. Adding a 10% safety cushion, purchase 74 bags of 80-lb mix.

Concrete Volume

1.48 yd³

40.0 cubic feet

80-lb Bags

74 bags

67 exact + 10% waste

60-lb Bags

98 bags

89 exact + 10% waste

Gravel Base (4")

2.3 tons

1.63 cubic yards

Customize or Adjust This 10×12 ft Project

Pre-filled with standard 10×12 ft measurements. Change depth or waste margins below to update quantities in real time.

Concrete

1.63 yd³

80 lb bags

74

60 lb bags

98

  • Concrete mix, 80 lb

    74 bags
  • Concrete mix, 60 lb

    98 bags
  • Concrete mix, 40 lb

    147 bags
  • Ready-mix concrete

    44 ft³

    1.63 yd³
  • Base gravel

    ≈ 2.29 tons

    1.63 yd³
Enter your local prices to see an estimated cost.

Bagged and bulk options are alternatives — the total uses the cheapest one you price.

10×12 ft Material Takeoff Breakdown

Slab ThicknessExact Volume80-lb Bags (+10%)60-lb Bags (+10%)Ready-Mix Order
4 inches (Shed/Patio)1.48 yd³74 bags (67 exact)98 bags (89 exact)1.75 yd³
5 inches (Hot Tub)1.85 yd³92 bags (83 exact)123 bags (109 exact)2.0 yd³
6 inches (Workshop)2.22 yd³110 bags (100 exact)147 bags (134 exact)2.5 yd³

Contractor & Builder Notes for 10×12 ft

  • ✓Use #4 rebar (½-inch) spaced in a 16" grid rather than wire mesh (welded wire fabric often ends up pressed to the dirt floor where it provides zero structural strength).

Frequently Asked Questions: 10×12 ft

How many bags of concrete for a 10x12 slab?

A 4-inch 10×12 slab requires 67 bags of 80-lb concrete (exact) or 74 bags with 10% safety margin.