10×10 ft Material Takeoff

10×10 Concrete Slab Calculator: Bags & Yards Takeoff

To pour a standard 10×10-foot concrete slab at 4 inches thick, you need 56 bags of 80-lb concrete or 74 bags of 60-lb concrete (exact volume of 1.23 cubic yards). Factoring in a standard 10% buffer for subgrade variations and form deflection, purchase 62 bags (80-lb) or 82 bags (60-lb).

Concrete Volume

1.23 yd³

33.3 cubic feet

80-lb Bags

62 bags

56 exact + 10% waste

60-lb Bags

82 bags

74 exact + 10% waste

Gravel Base (4")

1.9 tons

1.36 cubic yards

Customize or Adjust This 10×10 ft Project

Pre-filled with standard 10×10 ft measurements. Change depth or waste margins below to update quantities in real time.

Concrete

1.36 yd³

80 lb bags

62

60 lb bags

82

  • Concrete mix, 80 lb

    62 bags
  • Concrete mix, 60 lb

    82 bags
  • Concrete mix, 40 lb

    123 bags
  • Ready-mix concrete

    36.7 ft³

    1.36 yd³
  • Base gravel

    ≈ 1.91 tons

    1.36 yd³
Enter your local prices to see an estimated cost.

Bagged and bulk options are alternatives — the total uses the cheapest one you price.

10×10 ft Material Takeoff Breakdown

Slab ThicknessExact Volume80-lb Bags (+10%)60-lb Bags (+10%)Ready-Mix Order
4 inches (Shed/Patio)1.23 yd³62 bags (56 exact)82 bags (74 exact)1.5 yd³
5 inches (Hot Tub)1.54 yd³77 bags (69 exact)103 bags (92 exact)1.75 yd³
6 inches (Driveway)1.85 yd³92 bags (83 exact)123 bags (109 exact)2.0 yd³

Contractor & Builder Notes for 10×10 ft

  • ✓Compact 4 inches of crushed gravel base (#57 or 3/4-minus stone) beneath the slab to eliminate winter frost heave and settling cracks.
  • ✓Install ½" rebar grid on 18-inch centers supported by plastic rebar chairs so the steel sits in the center third of the slab depth.

Frequently Asked Questions: 10×10 ft

How many 80 lb bags of concrete do I need for a 10x10 slab at 4 inches?

You need 56 bags exact. With a 10% margin for form flex and uneven ground, purchase 62 bags.

Is it cheaper to order a concrete truck or buy bags for a 10x10 slab?

At 1.23 to 1.5 yards, material costs are close ($350–$450). However, ready-mix companies often charge a 'short-load fee' ($100–$200) for orders under 4 or 5 yards. If you have helpers, mixing bags or renting a portable towable mixer saves money.